Agenda Item
Meeting Date: 10/7/2019 - 6:00 PM
Category: Operations Services
Type: Action
Subject: Discussion, motion and vote on to approve or disapprove Change Order #02 for the new Elementary School 16 Bond Project – Value Engineering; resulting in a net decrease of $294,542.00 to Manhattan Construction Company's contract with payment from Bond Funds. This is pursuant to Manhattan Construction Company's contract dated December 10, 2018. All bidding was conducted pursuant to the Oklahoma Competitive Bidding Act. B. Tolomeo
:
Enclosure:
File Attachment:
Summary: The New Elementary School 16 Bond Project bid packages were received and opened April 30, 2019 and approved at the May 13, 2019 BOE meeting. At that time, it was discussed that an additional $294,542.00 was needed to be value engineered out of the project. This change order is a result of that value engineering.

Please see below for a breakdown:
Original GMP 2 Sum Contract $16,862,311.00
Previous Change Orders $ 260,628.00
Change Order #2 - Net Decrease $ -294,542.00
New Sum Contract $16,858,397.00
Funding: Bond Funds
Recommendation: Approve
Approvals:
Recommended By:
Signed By:
Courtney Cheatwood - Admin Asst to COO
Signed By:
Michelle Bergwall - Chief Operating Officer
Signed By:
Janet Dunlop - Superintendent